STATEMENT OF METHODOLOGY FOR INSTALLATION OF PERFORATED PIPE

TITLE: STATEMENT OF METHODOLOGY FOR INSTALLATION OF PERFORATED PIPE PURPOSE: The puprpose of this methodology is to illustrate the guidelines and procedures on the installation of Perforated Pipeping and underdrain works. SCOPE: The work procedure shall apply to Plumbing System for the Construction of all permanent and major temporary works. PROCEDURES: A. PRE-INSTALLATION 1. Secure the approved plans and drawings to be used for the activity 2. Verify if the area is ready for the activity 3. prepare all the  materials needed based on the approved material submittals. Materials should be checked and inspected upon delivery prior to installation. 4. Prepare all the required manpower, tools and equipments, and PPE for the installation. 5. Secure all the required work permits and safety permits prior to exevution of activities. B. INSTALLATION PROCEDURE: 1. Drill holes in the PVC Pipe. The hole diameter shall be 13mm with spacing of 150mm staggered or as recommended by the designers and Co

Statement of Methodology for the Installation of PPR Pipes for Waterline

    

TITLE: METHOD STATEMENT FOR THE INSTALLATION OF PPR PIPES FOR WATER LINE



1.PURPOSE

The Purpose of this method statement is to detail the procedure of Jointing of PPR-PN20 Pipes and Fittings for Potable and Non-Potable Water line. Ensure that proper installation procedure shall be implemented in accordance with existing general provisions.

2. SCOPE OF WORK

The work under this section includes providing all manpower, tools and equipment’s for jointing PPR Pipes and fittings.

3. PROCEDURE

Secure work permits before proceeding to the required work.

         Make sure that PPE's are complete.

Prepare the following tools and equipments:

- Pipe Cutter - Meter Tape

- Fusion Machine - Extension Cord

- Socket Welder - Clean Cloth

- Pencil / Marker

Layout the pipe routing on the walls and do the chipping works.

Cut the pipes rectangular with pipe cutters. Take care that the pipe axis is free from burrs or cutting debris and remove where necessary. Mark the welding depth at the end of the pipe according to the socket depth of the fittings.

Clean the socket and spigot with cleansing clothes.

After the welding machine reaches the necessary operating temperature, push the end of the pipe and fittings, without turning, up to the welding deep into the welding tool. Heat up the pipe’s spigot and fittings socket according to the following heating time.

After heating time, quickly remove the pipe and the fittings from the welding tools. Join them immediately without turning, until the marked welding depth is covered by the bead of the PPR from fittings.

The joint elements have to be fixed during the specified assembly time. After cooling period, the fused joint is ready for use.

Install the soldered pipes and fittings.

TABLE 2 - PPR TIME TABLE



Comments

  1. Casinos near Casino, St. Louis - Mapyro
    Hotels near Casino, 이천 출장샵 St. Louis, Missouri. Search for 광주광역 출장샵 the nearest Casino to Casino, St. Louis. 안양 출장마사지 Mapyro is your best 인천광역 출장안마 resource for finding hotels, 영천 출장안마 places to stay closest to

    ReplyDelete

Post a Comment

Popular posts from this blog

Statement of Methodology for Gravity Leak Test (NON PRESSURIZED PIPING SYSTEM)

TITLE: GRAVITY LEAK TEST (NON PRESSURIZED PIPING SYSTEM) 1. Purpose       The purpose of this method statement is to detail the Hydrostatic Test for Non-Pressurized Piping System. Ensure that proper installation procedure shall be implemented in accordance with existing general provision 2. Scope of Work The work under this section includes providing all manpower, tools and equipments for hydrostatic testing.  3.    Procedure • Make sure that all tools and PPE’s are complete. • Secure work permits before proceeding to the required work. • Prepare all the following needed tools for testing. - Motorized Test Pump - Testing Manifold - Pipe Wrench - Calibrated Pressure Gauge (Refer to attached sticker) - Adjustable Wrench - Masking Tape - Drum and Hose • Prepare the necessary documents such as inspection and testing permits with specified key plan location attached as well as other pertinent documents needed. • Check all conne

STATEMENT OF METHODOLOGY FOR CONSTRUCTION OF DRAINAGE SYSTEM

  TITLE: CONSTRUCTION OF DRAINAGE SYSTEM 1 SCOPE This method statement deals with surveys and layout, excavation, pipe laying, pipe collaring and backfilling of drainage system in the preparation of drainage box to complete the drainage line. 2 REFERENCE DOCUMENTS 2.1 Project Specification 2.2 Approved Plans 2.3 ITP – Inspection Test Plan 3 WORK PROCEDURE 3.1 Survey and Layout A. Preparation • Orientation of Workers or toolbox meeting before start of work. • Wear complete personal protective equipment always on the jobsite. • Secure work permit based on the scope of work to be executed. • Review plans for what and where the activity must be conducted. • Clear the area and install barricades before execution of the activity. • Ensure that all submittals are approved and signed. B. Execution • Ensure that the request for layout was submitted to survey group a day before the execution of activity. • Provide work activity permit prior to start the activity. •

Statement of Methodology for Pipe Sleeving

TITLE: METHOD STATEMENT FOR  SLEEVING WORK 1.Purpose ● The Purpose of this method statement is to detail the procedure of sleeving works. Ensure that proper installation procedure shall be implemented in accordance with existing general provisions. 2. Scope of Work ● The work under this section includes providing all manpower, tools and equipment’s for jointing installation of sleeves. 3. Procedure ● Make sure that all  tools and PPE’s are complete. ● Secure work permits before proceeding to the required work. ● Prepare all the following tools needed for the installation of sleeves. - Plum bob - Measuring tape - Level bar - Adjustable Wrench - A-type Ladder ● The length of pipe sleeve shall be the same as to the t