TITLE: STATEMENT OF METHODOLOGY FOR INSTALLATION OF PERFORATED PIPE PURPOSE: The puprpose of this methodology is to illustrate the guidelines and procedures on the installation of Perforated Pipeping and underdrain works. SCOPE: The work procedure shall apply to Plumbing System for the Construction of all permanent and major temporary works. PROCEDURES: A. PRE-INSTALLATION 1. Secure the approved plans and drawings to be used for the activity 2. Verify if the area is ready for the activity 3. prepare all the materials needed based on the approved material submittals. Materials should be checked and inspected upon delivery prior to installation. 4. Prepare all the required manpower, tools and equipments, and PPE for the installation. 5. Secure all the required work permits and safety permits prior to exevution of activities. B. INSTALLATION PROCEDURE: 1. Drill holes in the PVC Pipe. The hole diameter shall be 13mm with spacing of 150mm staggered or as recommended by the designers an...
TITLE: GRAVITY LEAK TEST (NON PRESSURIZED PIPING SYSTEM) 1. Purpose The purpose of this method statement is to detail the Hydrostatic Test for Non-Pressurized Piping System. Ensure that proper installation procedure shall be implemented in accordance with existing general provision 2. Scope of Work The work under this section includes providing all manpower, tools and equipments for hydrostatic testing. 3. Procedure • Make sure that all tools and PPE’s are complete. • Secure work permits before proceeding to the required work. • Prepare all the following needed tools for testing. - Motorized Test Pump - Testing Manifold - Pipe Wrench - Calibrated Pressure Gauge (Refer to attached sticker) - Adjustable Wrench - Masking Tape - Drum and Hose • Prepare the necessary documents such as inspection and testing permits with specified key plan location attached as well as other pertinent document...