STATEMENT OF METHODOLOGY FOR INSTALLATION OF PERFORATED PIPE

TITLE: STATEMENT OF METHODOLOGY FOR INSTALLATION OF PERFORATED PIPE PURPOSE: The puprpose of this methodology is to illustrate the guidelines and procedures on the installation of Perforated Pipeping and underdrain works. SCOPE: The work procedure shall apply to Plumbing System for the Construction of all permanent and major temporary works. PROCEDURES: A. PRE-INSTALLATION 1. Secure the approved plans and drawings to be used for the activity 2. Verify if the area is ready for the activity 3. prepare all the  materials needed based on the approved material submittals. Materials should be checked and inspected upon delivery prior to installation. 4. Prepare all the required manpower, tools and equipments, and PPE for the installation. 5. Secure all the required work permits and safety permits prior to exevution of activities. B. INSTALLATION PROCEDURE: 1. Drill holes in the PVC Pipe. The hole diameter shall be 13mm with spacing of 150mm staggered or as recommended by the designers and Co

Statement of Methodology for Pipe Sleeving

TITLE: METHOD STATEMENT FOR  SLEEVING WORK


1.Purpose

The Purpose of this method statement is to detail the procedure of sleeving works. Ensure that proper installation procedure shall be implemented in accordance with existing general provisions.

2. Scope of Work

The work under this section includes providing all manpower, tools and equipment’s for jointing installation of sleeves.

3. Procedure

Make sure that all  tools and PPE’s are complete.

Secure work permits before proceeding to the required work.

Prepare all the following tools needed for the installation of sleeves.

- Plum bob

- Measuring tape

- Level bar

- Adjustable Wrench

- A-type Ladder

The length of pipe sleeve shall be the same as to the thickness of the finished wall.

Determine the size of sleeve to be used.  See Table 1 below.

Insert the sleeve first and assure the pipe elevation is correct. Use level bar to check the straightness of the pipe.

Use a plumb bob to locate the exact location of the sleeve within the CHB wall.

Insert rock wool inside the sleeve; Make sure that the annulus between the pipe and pipe sleeve is even having the same centerline. The rock wool will act as a spacer and temporary sealant against cement during CHB wall finishing.

Table 1: Pipe Sleeve Schedule


















Comments


  1. What’s up, every time I used to check blog posts here in the early hours in the break of day, for the reason that I enjoy to gain knowledge of more and more. Get more information at A335 P11. As I am in fact eager of reading this web site’s post to be updated regularly. It includes nice stuff.

    ReplyDelete


  2. I will prefer this blog because it has much more informative stuff. Visit ss 304 flanges for more related information and knowledge.

    ReplyDelete
  3. I agree with a lot of the points you made in this article. If you are looking for the stainless steel pipe suppliers in India, then visit manishasteel. I appreciate the work you have put into this and hope you continue writing on this subject.

    ReplyDelete
  4. Thanks for such a pleasant post. This post loaded with lots of useful information. Keep it up. If you are looking for the best information and suggestions related to alloy steel plate suppliers then visit tritonalloysinc.

    ReplyDelete
  5. first off, a hearty thanks to you. Your blog is awesome and completely knowledgeable and I completely satisfied with the reading. Keep your work spread till long after. For more SS 321 pipe suppliers related information visit triloksteel.Certainly, you are Right!!

    ReplyDelete

Post a Comment

Popular posts from this blog

Statement of Methodology for Gravity Leak Test (NON PRESSURIZED PIPING SYSTEM)

TITLE: GRAVITY LEAK TEST (NON PRESSURIZED PIPING SYSTEM) 1. Purpose       The purpose of this method statement is to detail the Hydrostatic Test for Non-Pressurized Piping System. Ensure that proper installation procedure shall be implemented in accordance with existing general provision 2. Scope of Work The work under this section includes providing all manpower, tools and equipments for hydrostatic testing.  3.    Procedure • Make sure that all tools and PPE’s are complete. • Secure work permits before proceeding to the required work. • Prepare all the following needed tools for testing. - Motorized Test Pump - Testing Manifold - Pipe Wrench - Calibrated Pressure Gauge (Refer to attached sticker) - Adjustable Wrench - Masking Tape - Drum and Hose • Prepare the necessary documents such as inspection and testing permits with specified key plan location attached as well as other pertinent documents needed. • Check all conne

STATEMENT OF METHODOLOGY FOR CONSTRUCTION OF DRAINAGE SYSTEM

  TITLE: CONSTRUCTION OF DRAINAGE SYSTEM 1 SCOPE This method statement deals with surveys and layout, excavation, pipe laying, pipe collaring and backfilling of drainage system in the preparation of drainage box to complete the drainage line. 2 REFERENCE DOCUMENTS 2.1 Project Specification 2.2 Approved Plans 2.3 ITP – Inspection Test Plan 3 WORK PROCEDURE 3.1 Survey and Layout A. Preparation • Orientation of Workers or toolbox meeting before start of work. • Wear complete personal protective equipment always on the jobsite. • Secure work permit based on the scope of work to be executed. • Review plans for what and where the activity must be conducted. • Clear the area and install barricades before execution of the activity. • Ensure that all submittals are approved and signed. B. Execution • Ensure that the request for layout was submitted to survey group a day before the execution of activity. • Provide work activity permit prior to start the activity. •