Skip to main content

Posts

Showing posts with the label General Engineering

STATEMENT OF METHODOLOGY FOR INSTALLATION OF PERFORATED PIPE

TITLE: STATEMENT OF METHODOLOGY FOR INSTALLATION OF PERFORATED PIPE PURPOSE: The puprpose of this methodology is to illustrate the guidelines and procedures on the installation of Perforated Pipeping and underdrain works. SCOPE: The work procedure shall apply to Plumbing System for the Construction of all permanent and major temporary works. PROCEDURES: A. PRE-INSTALLATION 1. Secure the approved plans and drawings to be used for the activity 2. Verify if the area is ready for the activity 3. prepare all the  materials needed based on the approved material submittals. Materials should be checked and inspected upon delivery prior to installation. 4. Prepare all the required manpower, tools and equipments, and PPE for the installation. 5. Secure all the required work permits and safety permits prior to exevution of activities. B. INSTALLATION PROCEDURE: 1. Drill holes in the PVC Pipe. The hole diameter shall be 13mm with spacing of 150mm staggered or as recommended by the designers and Co

STATEMENT OF METHODOLOGY FOR CONSTRUCTION OF DRAINAGE SYSTEM

  TITLE: CONSTRUCTION OF DRAINAGE SYSTEM 1 SCOPE This method statement deals with surveys and layout, excavation, pipe laying, pipe collaring and backfilling of drainage system in the preparation of drainage box to complete the drainage line. 2 REFERENCE DOCUMENTS 2.1 Project Specification 2.2 Approved Plans 2.3 ITP – Inspection Test Plan 3 WORK PROCEDURE 3.1 Survey and Layout A. Preparation • Orientation of Workers or toolbox meeting before start of work. • Wear complete personal protective equipment always on the jobsite. • Secure work permit based on the scope of work to be executed. • Review plans for what and where the activity must be conducted. • Clear the area and install barricades before execution of the activity. • Ensure that all submittals are approved and signed. B. Execution • Ensure that the request for layout was submitted to survey group a day before the execution of activity. • Provide work activity permit prior to start the activity. •

How to create Statement of Methodology?

Before we start, one must know that setting Work Methodologies is very important especially in a medium and large scale projects where your Client has their own established parameters prior to execution of work. They will require you to submit your Statement of Methodologies to complete the project before they allow you to mobilize. Thus, it will result to further delay of your project. Here, we are going to set a simple guidelines on what your Statement of Methodology must contain before you execute your activity: I. Title Indicate the specific title of the work activity II. Table of Contents This one is optional. You may include this section in your MS (Statement of Methodology) to make it presentable. Some General contractors are requiring their subcontractors to put Table of Contents in their submitted MS. III. Purpose Be specific in stating the purpose of your MS IV. Scope of work Briefly describe the content of your Statement of Methodology. V. Tools and Materials Specify all the