TITLE: STATEMENT OF METHODOLOGY FOR INSTALLATION OF PERFORATED PIPE PURPOSE: The puprpose of this methodology is to illustrate the guidelines and procedures on the installation of Perforated Pipeping and underdrain works. SCOPE: The work procedure shall apply to Plumbing System for the Construction of all permanent and major temporary works. PROCEDURES: A. PRE-INSTALLATION 1. Secure the approved plans and drawings to be used for the activity 2. Verify if the area is ready for the activity 3. prepare all the  materials needed based on the approved material submittals. Materials should be checked and inspected upon delivery prior to installation. 4. Prepare all the required manpower, tools and equipments, and PPE for the installation. 5. Secure all the required work permits and safety permits prior to exevution of activities. B. INSTALLATION PROCEDURE: 1. Drill holes in the PVC Pipe. The hole diameter shall be 13mm with spacing of 150mm staggered or as recommended by the designers and Co

STATEMENT OF METHODOLOGY FOR CONSTRUCTION OF DRAINAGE SYSTEM

 


TITLE: CONSTRUCTION OF DRAINAGE SYSTEM


1 SCOPE

This method statement deals with surveys and layout, excavation, pipe laying, pipe collaring and backfilling of drainage system in the preparation of drainage box to complete the drainage line.

2 REFERENCE DOCUMENTS

2.1 Project Specification

2.2 Approved Plans

2.3 ITP – Inspection Test Plan

3 WORK PROCEDURE

3.1 Survey and Layout

A. Preparation

Orientation of Workers or toolbox meeting before start of work.

Wear complete personal protective equipment always on the jobsite.

Secure work permit based on the scope of work to be executed.

Review plans for what and where the activity must be conducted.

Clear the area and install barricades before execution of the activity.

Ensure that all submittals are approved and signed.


B. Execution

Ensure that the request for layout was submitted to survey group a day before the execution of activity.

Provide work activity permit prior to start the activity.

Coordinate with the survey team to determine the exact location of the drainage lines prior to excavation.


3.2 Excavation

Provide work activity permit prior to start the activity.

Ensure that the area is free from obstructions.

Make reference line marking for proper elevation of trench to excavate prior to pipe laying.

Trenches for drainage pipes may be excavated as soon as the subgrade is already prepared provided that there is sufficient cover over the pipes that will protect the pipes from crushing during rolling compaction activity. Otherwise, trenching shall be made only after sub-base is prepared and before laying off the base course.

The trench shall be excavated to the required depth, given by the survey or line grade shown on the plan. The bottom of the trench shall be shaped to conform to the shape of pipe for at least ten percent of its outer diameter. The width of the trench shall not be greater than necessary to permit satisfactory jointing and thorough tamping of bedding material under and around pipe.

Where rock and hard layer ae encountered, the rock shall be excavated to a minimum over depth rock excavation and all excess trench excavation shall be backfilled and thoroughly tamped with loose moist earth or gravel without big stones. This selected backfill shall be graded and prepared to provide a firm and uniform bearing throughout the entire length of the pipe.

Inspection

Provide survey report.
Request for inspection shall be submitted (to inspect the depth and alignment of drainage) to operations and QA/QC in advance as per approved Project Specification and plan. 
Any comment or minor changes has to be fulfilled and re-inspection must be carried out to satisfy the design and the Consultant’s requirements.

3.3. Pipe Laying

A. Preparation
Orientation of workers or toolbox meeting before start of work.
Wear complete personal protective equipment always on the jobsite.
Secure work permit based on the scope of work to be executed.
Review plans for what and where the activity must be conducted.
Clear the area and install barricades before execution of the activity.
Ensure that all submittals are approved and signed.
Check the condition of base where the pipes will be laid.
Make sure that the pipes (RCP) are in good condition and passed the quality test/Three Edge Test.
Prepare and make sure the good condition of “lifter” that will be used in laying large diameter pipes.

B. Execution

Ensure that the area is free from obstructions
Make reference line marketing for correct elevation needed in drainage system to avoid backflow and ponding of water.
Installation of ladder is required for safe ingress and egress of workers works on excavation area.
In laying of larger pipes, make sure that there are no workers under the excavation area while lifting operation are in progress.
Pipes shall be layed carefully true to lines and grades shown on the drawings or as directed by the engineer with the groove update. The pipe section shall be layed and filled to form a smooth and uniform invert when completed. All joints shall be filled with mortar composed of one part portland cement and three parts of cleaned graded sand passing #8 sieve with enough water added to obtain proper consistency.
A shallow excavation is made underneath the pipe of the groove end and is filled with mortar. The tongue and groove ends of the pipe also should be well cleaned and thoroughly soaked with water just before the joiint is made. Cement mortar is then applied to the lower portion of the groove end of the pipe being laid. The tongue end is then inserted to the groove end of the first pipe until mortar is squeezed out on the interior and exterior surface of the pipe is then cleaned of all extruding mortar and the remaining annular space is filled with mortar. Sufficient additional mortar shall be used to form a band round the outside of the joint.
Water shall be kept out of the trench until the joint has set. Any pipe that has grade or joint disturbed after laying shall be out and relaid.
Pipes and accessories shall be handled as such manner as to ensure placement in the trench in sound undamaged condition. Cutting shall be done only when necessary in neat and workmanlike manner without damaging the pipe. The contractor shall be responsible for and shall take all necesssary precaution to protect and preserve all existing surface and sub-surface structures. He shall provide permanent repairs for any structures damaged thru his negligence.

3.4 Pipe Collaring

Make sure the proper ratio of 1:2.5 for cement and sand with water-cement ratio of 0.4 is followed.
Follow the proper thickness of cement mortar base on the plan.
The presence of the site QA/QC engineer is needed for adjustment of the mixture of the concrete if necessary.

3.5 Backfilling and Compaction

Ensure that the area is free from obstructions.
Ensure that there are no materials and workers on the excavated area before backfilling.
Make reference line and markings for correct elevation needed for drainage system to avoid backflow and ponding of water.
Compaction must be nade every 250mm layer of backfill of water by water compaction and use of walk-behind compactor.
After the compaction, the area must undergo inn FDT to satisfy the specification of the project.

3.6 Construction of Drainage Manholes

Ensure that all the area are free from all obstructions.
Make reference line and markings for correct elevation and station of manholes.
Trim to meet he proper dimensions of mahole flooring then pour with lean concrete / gravel bedding.
Bend, fabricate and install rebars of manhole when pour with concrete for flooring.
Proceed to formworks for walls, pour with concrete that meet the required design.
Provide ladder rung to the manhole to the required depth and also the lot connections.
Install CHB and plaster for finishing.
Installation of scaffolding and and p;atform is required in construction of manholes 3 meters and above in height.
Install the surface cover.

3.7 Flow Test

3.7.1 Materials
1. Floating device – Ping-pong/Styro Ball

3.7.2 Procedures
a. Prior to testing, inspect the drainage lines to be tested for possible clogged materials that may affect the flow test.
b. Manholes should be free from scrap materials and properly cleaned and should be supplied by sufficient ventilation.
c. Adequate source of clean water for continuous flushing shall be provided. Floating device or materials shall be used to determine the continuity and slope of the pipe line from one manhole to connecting manhole.
d. Choose the starting point/manhole and continuously pour water by using water truck to supply water.
e. The group shall move to the ending connection to verify if the floater reached its end point. If the ball is not seen on the endpoint, check the pipe for possible clogged pipes. Repeat the test otherwise.
f. After completing the above steps, record data on the report form.
g. After the testing, clean and organize the test area.

4 MAJOR PLANT AND EQUIPMENT
4.1 Backhoe
4.2 Concrete vibrator
4.3 Skidloader
4.4 Mixing Board
4.5 One Bagger
4.6 Water truck

5 QUALITY ASSURANCE/CONTROL
7.1 Tests
Refer to Project-WP-ITP–Inspection and Test Plan/Construction Specifications.

7.2 Measuring and Testing Equipment to be Calibrated
Survey Equipment
FDT Equipment (Sand cone/Nuclear Density Gauge)

7.3 Inspections
Refer to WP-ITP – Inspection Plans
Refer to WP-Forms – Inspection Checklists and Forms

7.4 Parties and Products Requiring Accreditation or Certification
N/A




Comments

  1. After read this post I understand new things and Knowledge of this. I find latest information about this topic ss 316 sheet suppliers If you wants relevant services then visit Perfect Impex.

    ReplyDelete
  2. This blog loaded with lots of new information. Really helpful down to the ground, happy to read such a useful post stainless steel pipe bends Must visit Kanak Metal & Alloys for this types services.

    ReplyDelete
  3. Your contents are completely awesome and share worthy. I really appreciate your efforts that you put on this. Keep sharing. For more Carbon Steel Pipe Fittings Manufacturers In India related information visit Viha Steel & Forging

    ReplyDelete
  4. Wonderful blog, Which help us to understand information easily and fast. Keep sharing more info on this tube fittings manufacturers Visit Oshwin Overseas to more relevant services.

    ReplyDelete
  5. Information is very informative also you can click Stainless Steel Pipe suppliers in India ,and get such type of info, this is the great resource to get such type of information.

    ReplyDelete
  6. Nice reading, I love your content. This is really a fantastic and informative post. Keep it up and if you are looking for super duplex fittings manufacturers then visit Rajendra Piping & Fittings.

    ReplyDelete
  7. Thanks for the blog loaded with so many information. Stopping by your blog helped me to get what I was looking for. Foundation Repair jacksonville

    ReplyDelete
  8. I really like your take on the issue. I now have a clear idea on what this matter is all about.. Gainesville FL Foundation Repair Company

    ReplyDelete
  9. I felt very happy while reading this site. This was really very informative site for me. I really liked it. This was really a cordial post. Thanks a lot!. Longview TX Foundation Repair Company

    ReplyDelete
  10. Being one of the most trusted excavation services in Melbourne, Australian Demolition & Excavations has landed in the ground to serve you with extraordinary upshots. We have been serving entire Australia happily for many years, and over time we have learned how to win the hearts of our dedicated and esteemed clients.

    ReplyDelete
  11. Lightweight Trench Box Wow, cool post. I'd like to write like this too - taking time and real hard work to make a great article... but I put things off too much and never seem to get started. Thanks though.

    ReplyDelete
  12. I’m going to read this. I’ll be sure to come back. thanks for sharing. and also This article gives the light in which we can observe the reality. this is very nice one and gives indepth information. thanks for this nice article... how to repair a house foundation

    ReplyDelete
  13. Pretty good post. I just stumbled upon your blog and wanted to say that I have really enjoyed reading your blog posts. Any way I'll be subscribing to your feed and I hope you post again soon. Big thanks for the useful info. Foundation Repair Tampa FL

    ReplyDelete
  14. I will prefer this blog because it has much more informative stuff. Visit Aluminum Pipe Suppliers In India for more related information and knowledge.

    ReplyDelete


  15. Hi there to everyone, the contents present at this web page are actually amazing for people knowledge, well, you can also visit nickel 200 tube suppliers for more vishalsteelindia related information and knowledge. Keep up the good work.

    ReplyDelete
  16. Thanks for a very interesting blog. What else may I get that kind of info written in such a perfect approach? I’ve a undertaking that I am simply now operating on, and I have been at the look out for such info. trench shoring systems

    ReplyDelete
  17. Authentic platform to find the leading nut bolt industry here. Deal with King Fasteners for Quality Flange Nut | Hex Weld Nut | Square nut etc. At true cost. If you are looking for best ASTM A240 SS 316 Foil Manufacturer you can visit Sonic Steels.

    ReplyDelete
  18. I do agree with many of the points you have made in this article. If you are looking for ASTM A790 Super Duplex S32750 Boiler Pipe., visit Shree Ashapura Steel Center. I like your content, they are very nice and very useful for us and this text is worth everyone's attention.

    ReplyDelete
  19. After reading this post, I gained new insights and information. I obtained the most recent SS 17-4ph Seamless Welded Pipe information; if you want similar services, please get in touch with Stanley Alloys.

    ReplyDelete
  20. I found just what I was seeking on your blog. It includes useful information regarding the Duplex 2205 Fasteners. Thank you for giving such useful information.

    ReplyDelete
  21. After exploring this blog, I discovered a wealth of material that has helped me get started. I am delighted to have found this type of blog Stainless Steel 18-8 Fasteners. For more information, please visit.

    ReplyDelete
  22. This article presents a compelling argument backed by solid evidence and research. It's refreshing to see an opinion piece that relies on facts rather than mere conjecture.
    UNS S32760 Seamless Welded Pipe

    ReplyDelete
  23. This article serves as a timely reminder of the importance of environmental conservation. The author's passion for the topic is contagious.
    Super Duplex S32760 Fasteners

    ReplyDelete
  24. I completely agree with your points in this blog post. It's refreshing to see someone articulate these ideas so clearly and concisely.
    UNS S32205 Sheets

    ReplyDelete
  25. I love how you broke down complex concepts in this blog post and made them easy to understand. It's clear that you have a knack for explaining things clearly.
    ASTM A240 316L SS Foils

    ReplyDelete
  26. I like that the author took the time to research the background of the matter. It enriches and broadens our understanding of the topic at hand.  visit  ST 52 Pipe Stockist for best best pipes . 

    ReplyDelete
  27. Your expert blog is useful. Your material and advice show that you want your audience to succeed. Your articles were informative. we Manufactured High-Quality UNS S31803 Round Bar 

    ReplyDelete
  28. I think this article does a good job of presenting both sides of the topic. Insightful and well-balanced, the author presents a variety of perspectives. For superior plates, check out Duplex Steel S32205 Plate

    ReplyDelete
  29. Your post has become my go-to source for keeping up with the latest changes and best practices in my field. I like that you cover a wide range of topics and talk about both technical and commercial problems so that you can reach a large audience. For the best pipes, go to Duplex Steel 2205 Seamless Pipe.

    ReplyDelete
  30. I always find myself coming back to your story. I like how you simplify hard concepts for me to digest. It's clear that you made an effort to read widely and express those results clearly and simply. If you need high-quality ASTM A312 SS 310 Seamless Pipe , you should come to us.

    ReplyDelete
  31. A tool organizer is a storage solution designed to keep your tools well-organized, easily accessible, and efficiently stored. It helps create a tidy workspace and enhances your overall productivity.

    ReplyDelete
  32. Ergonomic recumbent design & cushioned seats for maximum comfort

    adult tricycles

    ReplyDelete

Post a Comment

Popular posts from this blog

Statement of Methodology for Gravity Leak Test (NON PRESSURIZED PIPING SYSTEM)

TITLE: GRAVITY LEAK TEST (NON PRESSURIZED PIPING SYSTEM) 1. Purpose       The purpose of this method statement is to detail the Hydrostatic Test for Non-Pressurized Piping System. Ensure that proper installation procedure shall be implemented in accordance with existing general provision 2. Scope of Work The work under this section includes providing all manpower, tools and equipments for hydrostatic testing.  3.    Procedure • Make sure that all tools and PPE’s are complete. • Secure work permits before proceeding to the required work. • Prepare all the following needed tools for testing. - Motorized Test Pump - Testing Manifold - Pipe Wrench - Calibrated Pressure Gauge (Refer to attached sticker) - Adjustable Wrench - Masking Tape - Drum and Hose • Prepare the necessary documents such as inspection and testing permits with specified key plan location attached as well as other pertinent documents needed. • Check all conne

Statement of Methodology for Pipe Sleeving

TITLE: METHOD STATEMENT FOR  SLEEVING WORK 1.Purpose ● The Purpose of this method statement is to detail the procedure of sleeving works. Ensure that proper installation procedure shall be implemented in accordance with existing general provisions. 2. Scope of Work ● The work under this section includes providing all manpower, tools and equipment’s for jointing installation of sleeves. 3. Procedure ● Make sure that all  tools and PPE’s are complete. ● Secure work permits before proceeding to the required work. ● Prepare all the following tools needed for the installation of sleeves. - Plum bob - Measuring tape - Level bar - Adjustable Wrench - A-type Ladder ● The length of pipe sleeve shall be the same as to the t

STATEMENT OF METHODOLOGY FOR INSTALLATION OF PERFORATED PIPE

TITLE: STATEMENT OF METHODOLOGY FOR INSTALLATION OF PERFORATED PIPE PURPOSE: The puprpose of this methodology is to illustrate the guidelines and procedures on the installation of Perforated Pipeping and underdrain works. SCOPE: The work procedure shall apply to Plumbing System for the Construction of all permanent and major temporary works. PROCEDURES: A. PRE-INSTALLATION 1. Secure the approved plans and drawings to be used for the activity 2. Verify if the area is ready for the activity 3. prepare all the  materials needed based on the approved material submittals. Materials should be checked and inspected upon delivery prior to installation. 4. Prepare all the required manpower, tools and equipments, and PPE for the installation. 5. Secure all the required work permits and safety permits prior to exevution of activities. B. INSTALLATION PROCEDURE: 1. Drill holes in the PVC Pipe. The hole diameter shall be 13mm with spacing of 150mm staggered or as recommended by the designers and Co