TITLE: CONSTRUCTION OF DRAINAGE SYSTEM
1 SCOPE
This method statement deals with surveys and layout, excavation, pipe laying, pipe collaring and backfilling of drainage system in the preparation of drainage box to complete the drainage line.
2 REFERENCE DOCUMENTS
2.1 Project Specification
2.2 Approved Plans
2.3 ITP – Inspection Test Plan
3 WORK PROCEDURE
3.1 Survey and Layout
A. Preparation
• Orientation of Workers or toolbox meeting before start of work.
• Wear complete personal protective equipment always on the jobsite.
• Secure work permit based on the scope of work to be executed.
• Review plans for what and where the activity must be conducted.
• Clear the area and install barricades before execution of the activity.
• Ensure that all submittals are approved and signed.
B. Execution
• Ensure that the request for layout was submitted to survey group a day before the execution of activity.
• Provide work activity permit prior to start the activity.
• Coordinate with the survey team to determine the exact location of the drainage lines prior to excavation.
3.2 Excavation
• Provide work activity permit prior to start the activity.
• Ensure that the area is free from obstructions.
• Make reference line marking for proper elevation of trench to excavate prior to pipe laying.
• Trenches for drainage pipes may be excavated as soon as the subgrade is already prepared provided that there is sufficient cover over the pipes that will protect the pipes from crushing during rolling compaction activity. Otherwise, trenching shall be made only after sub-base is prepared and before laying off the base course.
• The trench shall be excavated to the required depth, given by the survey or line grade shown on the plan. The bottom of the trench shall be shaped to conform to the shape of pipe for at least ten percent of its outer diameter. The width of the trench shall not be greater than necessary to permit satisfactory jointing and thorough tamping of bedding material under and around pipe.
• Where rock and hard layer ae encountered, the rock shall be excavated to a minimum over depth rock excavation and all excess trench excavation shall be backfilled and thoroughly tamped with loose moist earth or gravel without big stones. This selected backfill shall be graded and prepared to provide a firm and uniform bearing throughout the entire length of the pipe.
Inspection
• Provide survey report.
Request for inspection shall be submitted (to inspect the depth and alignment of drainage) to operations and QA/QC in advance as per approved Project Specification and plan.
Any comment or minor changes has to be fulfilled and re-inspection must be carried out to satisfy the design and the Consultant’s requirements.
3.3. Pipe Laying
A. Preparation
• Orientation of workers or toolbox meeting before start of work.
• Wear complete personal protective equipment always on the jobsite.
• Secure work permit based on the scope of work to be executed.
• Review plans for what and where the activity must be conducted.
• Clear the area and install barricades before execution of the activity.
• Ensure that all submittals are approved and signed.
• Check the condition of base where the pipes will be laid.
• Make sure that the pipes (RCP) are in good condition and passed the quality test/Three Edge Test.
• Prepare and make sure the good condition of “lifter” that will be used in laying large diameter pipes.
B. Execution
• Ensure that the area is free from obstructions
• Make reference line marketing for correct elevation needed in drainage system to avoid backflow and ponding of water.
• Installation of ladder is required for safe ingress and egress of workers works on excavation area.
• In laying of larger pipes, make sure that there are no workers under the excavation area while lifting operation are in progress.
• Pipes shall be layed carefully true to lines and grades shown on the drawings or as directed by the engineer with the groove update. The pipe section shall be layed and filled to form a smooth and uniform invert when completed. All joints shall be filled with mortar composed of one part portland cement and three parts of cleaned graded sand passing #8 sieve with enough water added to obtain proper consistency.
• A shallow excavation is made underneath the pipe of the groove end and is filled with mortar. The tongue and groove ends of the pipe also should be well cleaned and thoroughly soaked with water just before the joiint is made. Cement mortar is then applied to the lower portion of the groove end of the pipe being laid. The tongue end is then inserted to the groove end of the first pipe until mortar is squeezed out on the interior and exterior surface of the pipe is then cleaned of all extruding mortar and the remaining annular space is filled with mortar. Sufficient additional mortar shall be used to form a band round the outside of the joint.
• Water shall be kept out of the trench until the joint has set. Any pipe that has grade or joint disturbed after laying shall be out and relaid.
• Pipes and accessories shall be handled as such manner as to ensure placement in the trench in sound undamaged condition. Cutting shall be done only when necessary in neat and workmanlike manner without damaging the pipe. The contractor shall be responsible for and shall take all necesssary precaution to protect and preserve all existing surface and sub-surface structures. He shall provide permanent repairs for any structures damaged thru his negligence.
3.4 Pipe Collaring
• Make sure the proper ratio of 1:2.5 for cement and sand with water-cement ratio of 0.4 is followed.
• Follow the proper thickness of cement mortar base on the plan.
• The presence of the site QA/QC engineer is needed for adjustment of the mixture of the concrete if necessary.
3.5 Backfilling and Compaction
• Ensure that the area is free from obstructions.
• Ensure that there are no materials and workers on the excavated area before backfilling.
• Make reference line and markings for correct elevation needed for drainage system to avoid backflow and ponding of water.
• Compaction must be nade every 250mm layer of backfill of water by water compaction and use of walk-behind compactor.
• After the compaction, the area must undergo inn FDT to satisfy the specification of the project.
3.6 Construction of Drainage Manholes
• Ensure that all the area are free from all obstructions.
• Make reference line and markings for correct elevation and station of manholes.
• Trim to meet he proper dimensions of mahole flooring then pour with lean concrete / gravel bedding.
• Bend, fabricate and install rebars of manhole when pour with concrete for flooring.
• Proceed to formworks for walls, pour with concrete that meet the required design.
• Provide ladder rung to the manhole to the required depth and also the lot connections.
• Install CHB and plaster for finishing.
• Installation of scaffolding and and p;atform is required in construction of manholes 3 meters and above in height.
• Install the surface cover.
3.7 Flow Test
3.7.1 Materials
1. Floating device – Ping-pong/Styro Ball
3.7.2 Procedures
a. Prior to testing, inspect the drainage lines to be tested for possible clogged materials that may affect the flow test.
b. Manholes should be free from scrap materials and properly cleaned and should be supplied by sufficient ventilation.
c. Adequate source of clean water for continuous flushing shall be provided. Floating device or materials shall be used to determine the continuity and slope of the pipe line from one manhole to connecting manhole.
d. Choose the starting point/manhole and continuously pour water by using water truck to supply water.
e. The group shall move to the ending connection to verify if the floater reached its end point. If the ball is not seen on the endpoint, check the pipe for possible clogged pipes. Repeat the test otherwise.
f. After completing the above steps, record data on the report form.
g. After the testing, clean and organize the test area.
4 MAJOR PLANT AND EQUIPMENT
4.1 Backhoe
4.2 Concrete vibrator
4.3 Skidloader
4.4 Mixing Board
4.5 One Bagger
4.6 Water truck
5 QUALITY ASSURANCE/CONTROL
7.1 Tests
Refer to Project-WP-ITP–Inspection and Test Plan/Construction Specifications.
7.2 Measuring and Testing Equipment to be Calibrated
Survey Equipment
FDT Equipment (Sand cone/Nuclear Density Gauge)
7.3 Inspections
Refer to WP-ITP – Inspection Plans
Refer to WP-Forms – Inspection Checklists and Forms
7.4 Parties and Products Requiring Accreditation or Certification
N/A
After read this post I understand new things and Knowledge of this. I find latest information about this topic ss 316 sheet suppliers If you wants relevant services then visit Perfect Impex.
ReplyDeleteThis blog loaded with lots of new information. Really helpful down to the ground, happy to read such a useful post stainless steel pipe bends Must visit Kanak Metal & Alloys for this types services.
ReplyDeleteYour contents are completely awesome and share worthy. I really appreciate your efforts that you put on this. Keep sharing. For more Carbon Steel Pipe Fittings Manufacturers In India related information visit Viha Steel & Forging
ReplyDeleteWonderful blog, Which help us to understand information easily and fast. Keep sharing more info on this tube fittings manufacturers Visit Oshwin Overseas to more relevant services.
ReplyDeleteInformation is very informative also you can click Stainless Steel Pipe suppliers in India ,and get such type of info, this is the great resource to get such type of information.
ReplyDeleteNice reading, I love your content. This is really a fantastic and informative post. Keep it up and if you are looking for super duplex fittings manufacturers then visit Rajendra Piping & Fittings.
ReplyDeleteThanks for the blog loaded with so many information. Stopping by your blog helped me to get what I was looking for. Foundation Repair jacksonville
ReplyDeleteVery useful info. Hope to see more posts soon!. Frisco TX Foundation Repair Company
ReplyDeleteI really like your take on the issue. I now have a clear idea on what this matter is all about.. Gainesville FL Foundation Repair Company
ReplyDeleteI felt very happy while reading this site. This was really very informative site for me. I really liked it. This was really a cordial post. Thanks a lot!. Longview TX Foundation Repair Company
ReplyDeleteBeing one of the most trusted excavation services in Melbourne, Australian Demolition & Excavations has landed in the ground to serve you with extraordinary upshots. We have been serving entire Australia happily for many years, and over time we have learned how to win the hearts of our dedicated and esteemed clients.
ReplyDeleteLightweight Trench Box Wow, cool post. I'd like to write like this too - taking time and real hard work to make a great article... but I put things off too much and never seem to get started. Thanks though.
ReplyDeleteI’m going to read this. I’ll be sure to come back. thanks for sharing. and also This article gives the light in which we can observe the reality. this is very nice one and gives indepth information. thanks for this nice article... how to repair a house foundation
ReplyDeletePretty good post. I just stumbled upon your blog and wanted to say that I have really enjoyed reading your blog posts. Any way I'll be subscribing to your feed and I hope you post again soon. Big thanks for the useful info. Foundation Repair Tampa FL
ReplyDeleteIt was such a good post. Visit astm a193 grade b8m. Thanks for sharing.
ReplyDeleteI will prefer this blog because it has much more informative stuff. Visit Aluminum Pipe Suppliers In India for more related information and knowledge.
ReplyDelete
ReplyDeleteHi there to everyone, the contents present at this web page are actually amazing for people knowledge, well, you can also visit nickel 200 tube suppliers for more vishalsteelindia related information and knowledge. Keep up the good work.
Thanks for a very interesting blog. What else may I get that kind of info written in such a perfect approach? I’ve a undertaking that I am simply now operating on, and I have been at the look out for such info. trench shoring systems
ReplyDeleteAuthentic platform to find the leading nut bolt industry here. Deal with King Fasteners for Quality Flange Nut | Hex Weld Nut | Square nut etc. At true cost. If you are looking for best ASTM A240 SS 316 Foil Manufacturer you can visit Sonic Steels.
ReplyDeleteI do agree with many of the points you have made in this article. If you are looking for ASTM A790 Super Duplex S32750 Boiler Pipe., visit Shree Ashapura Steel Center. I like your content, they are very nice and very useful for us and this text is worth everyone's attention.
ReplyDeleteAfter reading this post, I gained new insights and information. I obtained the most recent SS 17-4ph Seamless Welded Pipe information; if you want similar services, please get in touch with Stanley Alloys.
ReplyDeleteI found just what I was seeking on your blog. It includes useful information regarding the Duplex 2205 Fasteners. Thank you for giving such useful information.
ReplyDeleteAfter exploring this blog, I discovered a wealth of material that has helped me get started. I am delighted to have found this type of blog Stainless Steel 18-8 Fasteners. For more information, please visit.
ReplyDeleteThis article presents a compelling argument backed by solid evidence and research. It's refreshing to see an opinion piece that relies on facts rather than mere conjecture.
ReplyDeleteUNS S32760 Seamless Welded Pipe
This article serves as a timely reminder of the importance of environmental conservation. The author's passion for the topic is contagious.
ReplyDeleteSuper Duplex S32760 Fasteners
I completely agree with your points in this blog post. It's refreshing to see someone articulate these ideas so clearly and concisely.
ReplyDeleteUNS S32205 Sheets
I love how you broke down complex concepts in this blog post and made them easy to understand. It's clear that you have a knack for explaining things clearly.
ReplyDeleteASTM A240 316L SS Foils
I like that the author took the time to research the background of the matter. It enriches and broadens our understanding of the topic at hand. visit ST 52 Pipe Stockist for best best pipes .
ReplyDeleteYour expert blog is useful. Your material and advice show that you want your audience to succeed. Your articles were informative. we Manufactured High-Quality UNS S31803 Round Bar
ReplyDeleteI think this article does a good job of presenting both sides of the topic. Insightful and well-balanced, the author presents a variety of perspectives. For superior plates, check out Duplex Steel S32205 Plate .
ReplyDeleteYour post has become my go-to source for keeping up with the latest changes and best practices in my field. I like that you cover a wide range of topics and talk about both technical and commercial problems so that you can reach a large audience. For the best pipes, go to Duplex Steel 2205 Seamless Pipe.
ReplyDeleteI always find myself coming back to your story. I like how you simplify hard concepts for me to digest. It's clear that you made an effort to read widely and express those results clearly and simply. If you need high-quality ASTM A312 SS 310 Seamless Pipe , you should come to us.
ReplyDeleteA tool organizer is a storage solution designed to keep your tools well-organized, easily accessible, and efficiently stored. It helps create a tidy workspace and enhances your overall productivity.
ReplyDeleteErgonomic recumbent design & cushioned seats for maximum comfort
ReplyDeleteadult tricycles